Time-Period |
Activity |
| Stage 1 |
December 1999 - May 2000 |
Preliminary Planning 1 - 6 months |
| Stage 2 |
June 2000 - August 2000 |
Initiating the Self-Study 1 - 3 months |
| Stage 3 |
September 2000 - September 2001 |
Conducting the Self-Study 9 - 12 months |
| Stage 4 |
October 2001 - March 2002 |
Preparing for and Receiving the Visiting Committee 2
- 5 months |
| Stage 5 |
April 2002 - December 2002 |
Preparing for review and Action by the COC 5
- 7 months |